Tuesday - 4 May
The old washer and dryer are usable. For now.
The stucco came off the north wall. This wall will eventually be
removed once the room is framed out.
The plans left on the bench outside. If they
blow away or get rained on, Drew might have to fake it!
Thursday - 6 May
The rail has been removed and the floor laid out.
Thursday - 11 May
The pieces are all here, we just need to get them in the right order.
Spring winds are holding up progress.
Thursday - 13 May
Progress! The three outer walls are up.
Monday - 17 May
The roof beams and parapets have been added.
The back wall is probably coming out later this week.
Thursday - 20 May
The boys are back! The walls sheathing is done and roof too.
Time to break through the wall.
Tuesday - 25 May
The wall is history. Three out of four windows are installed.
Progress!
Wednesday - 26 May
Most of the electrical is in. The framework for the soffit is in place.
Next on the agenda, inspections.
Friday - 28 May
Almost ready for the three inspections: framing, plumbing, and electrical.
Roof is on (thunderstorms predicted for today). Vent for the stove is in. Top of stairs rebuilt.
Project shutting down for Memorial Day Weekend.